LuzOra july construction update: 30% complete and rising towards the 5th floor
July brought visible progress across LuzOra Residences on Dubai Islands, with the project now 30% complete overall. The 4th-floor structure is fully finished, while blockwork, MEP and plastering continue to advance across the ground floor, podiums and 1st residential level. LuzOra is now rising towards the 5th of 8 residential floors, bringing it closer to its expected handover within approximately 9–12 months.
Ground floor moves closer to internal finishing
1st podium nears blockwork completion
Blockwork on the 1st podium has reached 95%, leaving only the final sections to be completed before this stage is fully closed.
High-level MEP works are now at 40%, with service routes continuing across the level. Plastering has reached 15% and will progress further as the remaining blockwork and service installations are completed.
The 1st podium is gradually moving from its initial internal construction stage towards more detailed finishing works.
2nd podium advances to the next stage
The 2nd podium has reached an important point, with blockwork now 100% complete and the layout of the level fully established.
High-level MEP works have progressed to 15%, while plastering has reached 10%. With the walls now in place, the team can continue increasing activity across the building services and wall-finishing stages.

Residential layouts become more visible
On the 1st residential floor, blockwork has reached 85%, making the apartment layouts, corridors and internal divisions increasingly clear.
High-level MEP works are currently at 15%, as the electrical, plumbing and mechanical systems begin moving through the residential spaces. Plastering has also started and has reached 5%, marking the initial stage of preparing the apartment walls for their future finishes.
As these works progress, the 1st residential level is beginning to move beyond its open structure and towards the form of the completed residences.
4th-floor structure reaches 100%
Both the vertical and horizontal structural works on the 4th floor are now 100% complete.
The columns, structural walls and floor slab have all been completed, giving the level its full structural form and allowing construction to continue upwards.
LuzOra is now rising towards the 5th of 8 residential floors, making the development increasingly visible across its location on Dubai Islands.
Fully furnished lobby opening soon
Progress is not limited to the main building structure. The fully furnished LuzOra lobby will also officially open soon, offering a closer look at the interior atmosphere planned for the development.
The upcoming reveal will showcase how the lobby’s furniture, finishes and design details come together to create the arrival experience for future residents and visitors.
Stay tuned for the official opening!
Moving closer to handover on Dubai Islands
With construction progressing across multiple levels, LuzOra is moving closer to its anticipated handover within approximately 9–12 months, positioning it among the earlier residential developments expected to be completed on Dubai Islands.
An earlier handover gives owners the opportunity to use, rent or professionally manage their properties sooner. By reserving a unit during the current construction stage, buyers can enter earlier and prepare to start earning from their property once it is ready.
Connect with us today to check availability and reserve your unit on Dubai Islands.
DIA Developments continues to grow, guided by the belief that real growth is not only measured by what is created, but by what is given back.
Stay connected: https://www.instagram.com/dia.developments/