Construction updates
LuzOra Residences construction
update: 50% complete as the
structure reaches the 7th floor
- Published
- Reading time
- 3 min

How far along is LuzOra Residences, really? As of September, DIA Developments' project on Dubai Islands is 50% complete, with the structure now reaching the 7th floor and the 8th floor slab already 90% done. While the frame climbs toward its final height, work inside the building is moving just as fast: plastering and MEP installations are advancing across the ground floor, both podium levels and the first residential floor. Here's a floor-by-floor look at where construction stands this month, and what it means for buyers and investors waiting on handover.
September in 60 secondsWhere LuzOra Residences stands in September
The biggest milestone this month is the halfway mark: LuzOra Residences is now 50% complete. The structure has reached the 7th floor, and with the 8th floor slab 90% finished, the project is getting close to completing the structure of all residential floors. At the same time, the lower levels are well past the frame stage, with blockwork almost entirely done and teams focused on plastering and MEP (mechanical, electrical and plumbing) works.


Ground floor moves into finishing
The ground floor is the most advanced part of the building. Blockwork is complete, plastering has reached 90%, and MEP works stand at 85%, which means the level is now entering its final finishing stage. For buyers, this is the first area where the building starts to look less like a construction site and more like the finished residence it's set to become.
1st podium: plastering 80% complete
One level up, the 1st podium is catching up quickly. Blockwork is 95% complete, MEP works are at 75%, and plastering has reached 80%. With these works moving at a steady pace, the podium is getting closer to interior finishing.
1st residential floor takes shape
The first residential floor is where buyers can start to picture their future homes. Blockwork is complete, plastering is at 90%, and MEP works are at 20%, so apartment layouts, corridors and internal spaces are now clearly defined. Walking the floor, you can already see how the units are arranged and how residents will move through the building. Want to explore the layouts before your next visit? The 3D tour lets you walk through LuzOra Residences from anywhere.

A first look at the finished lobby
The lobby is complete, and this time it's a real photo, not a render. It's the first fully finished space in LuzOra Residences and a preview of the quality buyers can expect across the rest of the building as the other levels move into finishing.

Handover expected in around 11 months
With the structure at the 7th floor and the lower levels moving into finishing, LuzOra Residences is getting steadily closer to completion. Handover is currently expected in approximately 11 months. For investors, that timeline matters: the sooner the keys are handed over, the sooner you can start renting out or managing your unit and begin generating returns.